A basement is one of the few ways to add significant space to a London house without building out into the garden or up into the roof. It is also the most technically demanding domestic project there is. Underpinning, waterproofing, temporary works and party wall procedures all affect the cost and the programme. This guide sets out typical costs, what drives them and how a basement is built.
Basement conversion cost per m²
Construction cost only, before professional fees, statutory costs, contingency and VAT. Ranges run from standard to high specification.
| Type of basement | £ per m² | Typical programme |
|---|---|---|
| Existing cellar conversion (no major excavation) | £1,200 – £2,640 | 10–22 weeks |
| Lower-ground extension | £1,800 – £3,000 | 16–30 weeks |
| Under garden / lightwell extension | £1,800 – £3,000 | 16–34 weeks |
| New basement under an existing house (underpinned) | £2,400 – £4,420 | 20–40 weeks |
The type of basement has the biggest effect on cost. Converting an existing cellar mainly involves lowering the floor slightly, waterproofing and fitting out. A new basement under an existing house needs the whole structure underpinned, propped and excavated in sequence, and that is where most of the cost and risk sit.
What else goes into the budget
- Professional fees: architect and structural engineer, typically 12–17% of the construction cost. Basements also need temporary works design.
- Surveys: structural, drainage and ground investigation, typically £2,000–£4,000.
- Party wall: around £1,080–£2,160 per neighbour for typical London projects. Basements often sit at the upper end or above, because the works go below the neighbours’ foundations.
- Building Control, and planning where needed.
- Contingency: 12–18%. Existing buildings almost always reveal something once they are opened up.
- VAT at 20% on most residential work.
For a full budget for your property, use the project cost calculator.
Costs that are often missed
- spoil removal, which is expensive in central London where access is tight
- parking bay suspensions for skips and conveyors
- party wall awards and surveyor fees for each neighbour
- a Thames Water build-over agreement where sewers run under the works
- temporary works design and monitoring
Example basement budgets
Two typical London schemes at Mid specification in Zone 1–2, on a terraced house with two party wall neighbours. Figures are rounded to the nearest £1,000.
| Cellar conversion, 35 m² | New basement under the house, 50 m² | |
|---|---|---|
| Planning | Not needed | Needed |
| Construction | £68,000 – £87,000 | £166,000 – £207,000 |
| Professional fees | £8,000 – £15,000 | £20,000 – £35,000 |
| Contingency | £8,000 – £16,000 | £20,000 – £37,000 |
| Planning, Building Control, party wall | £3,000 – £7,000 | £4,000 – £8,000 |
| VAT (20%) | £17,000 – £25,000 | £42,000 – £57,000 |
| Total budget | £104,000 – £149,000 | £251,000 – £345,000 |
| Construction programme | 12–18 weeks | 24–34 weeks |
Party wall costs for basements are often above the standard band used here, because the works go below the neighbours’ foundations. To change the size, location or specification, use the project cost calculator.
How long does a basement take?
- Cellar conversion: roughly 3–5 months on site.
- Lower-ground or under-garden extension: roughly 4–8 months.
- New basement under an existing house: roughly 5–9 months, longer for large or complex schemes.
Design, planning and the party wall process come before this and can add several months.
Do I need planning permission for a basement?
- Refurbishing an existing cellar with no structural change or excavation often does not need planning permission, but check with your borough first.
- A new basement under the house, an extension under the garden or pavement, and any basement in a listed building or conservation area will typically need planning permission.
Borough policies differ
Many London boroughs have their own basement policies, so check the current rules for your address before design starts. In broad terms:
- Kensington & Chelsea: basement extensions limited to a single storey below ground, with strict control over total floor area and lightwells, and a strong focus on neighbouring amenity and structures.
- Westminster: high design standards and heritage protection. Basements under listed buildings face detailed scrutiny and often need conservation reports.
- Camden: full site investigation, flood risk assessment and sustainability reporting expected.
- Islington: emphasis on minimising disruption to neighbours, with controls on construction methods and noise.
- Hackney: expects energy-efficient design, careful spoil management and a robust construction method statement.
How a basement is built
1. Survey and feasibility
An experienced contractor and engineer assess the existing structure, the depth of the current footings, the water table and drainage, the ground conditions (London clay, sand, gravel), access for plant and spoil removal, and the effect on neighbouring properties.

2. Temporary works and propping
Excavating under a house affects the whole structure, so temporary supports are designed and installed first: steel props, beams, needle shoring and scaffold support where needed. Poor temporary works are one of the biggest risks on a basement project.
3. Underpinning and excavation
Underpinning extends the existing foundations downwards so the ground beneath can be dug out safely. Victorian and Edwardian houses usually use mass concrete underpinning. Deeper or more complex basements may need piled underpinning. Excavation is carried out in short bays, in a set sequence, to keep the structure stable.
4. Waterproofing
British Standard BS 8102 describes three types of waterproofing protection, which are often combined:
- Type A, barrier protection: tanking slurries or membranes applied to the structure.
- Type B, structurally integral: waterproof concrete.
- Type C, drained protection: a cavity drain membrane that collects water and takes it to a sump.
In London clay and high water table areas, a Type C drained system with sump pumps is the most common primary system. Whichever system is used, it should come with a guarantee and a maintenance plan.
5. Slab and drainage
A new reinforced slab, typically 200–300 mm thick, is cast with perimeter drainage channels. The drainage feeds a sump with twin pumps and a high-level alarm. A battery back-up is strongly recommended.
6. Steelwork and structural works
New steel frames, padstones and strengthened spine walls carry the house above the new open-plan space, and existing services are diverted.
7. MEP installation
Basements have little natural ventilation, so mechanical, electrical and plumbing design matters more than anywhere else in the house: MVHR (mechanical ventilation with heat recovery), humidity control, underfloor heating and lighting designed for low daylight.
8. Fit-out and completion
Insulated wall linings, screeds, ceilings, first- and second-fix services, bathrooms or kitchens, joinery and decoration. The work finishes with electrical and plumbing certification and Building Control sign-off.
Frequently asked questions
Will I need a party wall agreement?
Almost certainly. If the works affect a shared wall or go deeper than the neighbour’s foundations, the Party Wall etc. Act 1996 requires notices to be served, and an award is agreed before work starts.
Does a basement add value?
Usually it does, particularly where space is at a premium. How much depends on the area, the quality of the space and how well it connects to the rest of the house. A dark, poorly ventilated basement adds far less than a well-lit room that works with the house above.
What should I look for in a basement contractor?
Ask for completed basement projects you can see. Check experience with underpinning and temporary works, a formal contract (for example JCT), CDM compliance, and contractor’s all-risk, public liability and employer’s liability insurance.
How these figures are produced
The rates on this page are LACD’s own rate bands for building work in London, last reviewed in October 2026. They are the same rates used in our project cost calculator.
- Construction rates are per m² of floor area, at Standard, Mid and High specification.
- Location: Zone 1–2 ×1.15, Zone 3–4 ×1.07, outer London ×1.00. Listed buildings ×1.20, conservation areas ×1.08 and restricted access ×1.10 where they apply.
- On top of construction: professional fees of 12–17%, contingency of 12–18%, Building Control at £900–£2,640, party wall at £1,080–£2,160 per neighbour, a planning application at £660–£780 where needed, and VAT at 20%.
These are budget figures for early planning, not a quotation. A fixed price needs drawings, a structural survey and a site visit.